Service Component: Optimization (Bulk)
Case Study: M&B Pressure Investments

Mandate: Due to the many road upgrade programmes, an urgent need for higher tonnages of road-surfacing stone from Limpopo quarries was and is being required.

Challenges: Capacity constraints with regard to both locomotives and wagons on the side of Transnet Freight Rail. Thus LQ needed to move greater tonnages utilising fewer resources.

Solution: To execute more train trips per week using existing resources. The results are illustrated below in Figure 1 Tonnages moved 2007 to 2010.

Figure 1: Tonnages moved 2007-2010

2007/2008
2008/2009
2009/2010

Tonnages moved

156 050
213 180
319 078

Wagons used

120 wagons
80 wagons
80 wagons

Tonnage moved per wagon

1 300
2 665
3 988

Trip Plan

3 times per week
5 times per week
6 times per week

Train number

T8849
T8849
T8849